Procurement Process and Key Dates

Current/Future Procurements

Attached please find the most up-to-date information related to procurement for the three Community Venues projects. The City will maintain the website   www.cityoforlando.net/venues  and the Orlando Magic and Dr. Phillips Orlando Performing Arts Center (DPAC) will continually update the websites   www.orlandoeventscenter.com  and  www.orlandopac.org  to ensure the community has the most current information available on the three projects.

Throughout the procurement process, the City will ensure compliance with the Blueprint for a Sustainable Economic Impact. MWBE Certification with the City of Orlando typically takes 4 to 6 weeks. To review the City’s requirements (and for a copy of certification applications), please visit   www.cityoforlando.net/admin/mbe/index.html  or call the Minority and Women Business Enterprise Office at 407-246-2623.

For the latest information, documents, news, schedule and contact information on the Events Center, please link to   www.orlandoeventscenter.com   or call 407-916-2449. Email Events Center Request for Proposal (RFP) questions or general questions to: Pat Gallagher, Business Development & Strategy Manager, at   pgallagher@orlandomagic.com   or call 407-916-2449.

For the latest information, documents, news, schedule and contact information on the Performing Arts Center, please link to   www.orlandopac.org/   or call 407-839-0119. Email Request for Proposal (RFP) questions concerning the Dr. Phillips Orlando Performing Arts Center to: Hines (DPAC’s development manager), Attn: Mark Chenoweth,   Mark_Chenoweth@Hines.com . Email general questions and/or comments to: Hines (DPAC’s development manager), Attn: Chuck Watters,   Chuck_Watters@Hines.com .

The City of Orlando currently owns and operates the Florida Citrus Bowl Stadium and is responsible for the renovations to the facility. The City is in the process of developing information to be included in a request for proposal for prospective design-build firms. At this time, no other information is available, but will be updated at   www.cityoforlando.net/venues   when moving forward in the procurement process.

Community Venues Procurement Process and Key Dates

Updated:  July 30, 2008

 Note:  Target dates and meeting information are subject to change.

*Indicates actual date 

Venue

Project/Procurement Description

Responsible Party

Actual/Target Issue Date

Actual/Target Due Date

Actual/Target Selection/

Authorization

Notes/Selection

 

 

 

 

 

 

 

Events Center

Utility Relocations / Improvements Construction Procurement(s)

City

2008

2008

2008

 

Events Center

South Street Roadway, Streetscape, & Utility Improvements Design/Build Services Request for Proposals

City

5/18/2008*

6/9/2008*

8/4/2008

7/9/2008*

Gomez Construction Co. & GAI Consultants, Inc. Ranked #1, pending City Council Approval

 

Events Center

Site Utility Relocation Design Services – Continuing Services Agreement, Services Authorization –Various Utilities and Communication Duct Bank

City

 

 

6/23/2008*; 6/2/2008*; 4/21/2008*; 2/11/2008*; 9/10/2007*; 8/20/2007*

Carter-Burgess

Events Center

Parking Garage Design-Build Services Request for Proposals

City

 

11/25/2007*

12/26/2007*

6/2/2008*; 2/11/2008*

PCL Construction Services, Inc. selected

Events Center

Professional Service Firms (Threshold Inspection & Materials Testing) Request for Qualifications

Magic

3/10/2008*

3/27/2008*

6/2/2008*; 4/14/2008*

Universal Engineering Sciences, Inc. selected for Threshold Inspection.  Nodarse and Associates, Inc. ranked #1 for Construction Materials Testing & Inspection

Events Center

Site Utility Relocation Construction Procurement –Church/Hughey Sanitary – Rapid Response Contractors

City

5/1/2008*

5/22/2008*

5/28/2008*

A & M SI Construction Co., Inc.

Events Center

Streetscape – Professional Landscape Architecture Design Services Request for Qualification Statements

City

1/28/2008*

2/15/2008*

3/17/2008*

Glatting Jackson Kercher Anglin, Inc. ranked #1, pending successful negotiations

Events Center

Issuance of Tourist Development Tax Revenue Bonds, Series 2008 A, B & C

City

 

 

 

3/13/2008*

A & B: Citigroup Capital Markets and Goldman Sachs & Co.; C: Goldman Sachs & Co.

Events Center

Issuance of State Sales Tax Payments Revenue Bonds, Series 2007

City

2007

2/26/2008*

3/6/2008*

Regions Bank listed as Registrar and Paying Agent.  Jackson Securities LLC listed as Underwriter.

Events Center

M/WBE Coordinator Request For Proposals

Magic

9/17/2007*

10/3/2007*

3/4/2008*

Selected B&L Management Consulting Group, Inc. pending successful negotiations

Events

Site Utility Relocation Design Services – Continuing Services Agreement, Services Authorization –Retention Pond P6 Modifications

City

 

 

3/3/2008*

PEC Engineering

Events Center

Site Demolition Services – Continuing Services Agreements, Services Authorization

City

 

 

10/2007 – 1/2008*

HB Walker, Global

Events Center

Site Utility Relocation Construction Procurement – Division/Church Sanitary & Stormwater – Rapid Response Contractors

City

11/2007*

12/21/2007*

1/2008*

CE James

Events Center

Insurance Brokerage Services Request For Proposals

Magic

11/5/2007*

12/4/2007*

12/14/2007*

Marsh USA, Inc selected

Events Center

Traffic Analysis—Continuing Services Agreement, Services Authorization

City

 

 

 

11/12/2007*

GMB

Events Center

Construction Manager at Risk “Most Qualified” Request for Proposals

Magic

9/24/2007*

10/12/2007*

10/23/2007*

Selected Hunt Construction Group with Rey Group, R.L. Burns Inc., HZ Construction and Albu & Associates Inc, as in-association CM partners

Events Center

Environmental Remediation Request for Proposals

City

 

8/30/2007*

9/26/2007*

10/15/2007*

Geo-Cleanse

Events Center

Green Champion Request For Proposals

Magic

9/17/2007*

10/3/2007*

10/5/2007*

TLC selected

Events Center

Design Consultants Request for Qualifications

Magic

8/13/2007*

8/24/2007*

9/27/2007*

link to selection announcement

Events Center

Geotechnical Engineer Request for Qualifications

Magic

8/13/2007*

8/24/2007*

9/27/2007*

Nodarse selected

Events Center

Construction Manager at Risk Request for Qualifications

Magic

8/27/2007*

9/13/2007*

9/18/2007*

“Most Qualified” Firms: Hunt Construction; PCL Construction, Barton Malow, and JCB Construction joint venture; Skanska USA and JCB Construction joint venture; and Austin Commercial and Hardin Construction joint venture

Events Center

Design Professional Request for Proposals

Magic

5/30/2007*

6/21/2007*

8/3/2007*

HOK Sport, Walter P. Moore, Smith Seckman Reid selected

Events Center

Surveying Services—Continuing Services Agreement, Services Authorization

City

 

 

 

2006-2007*

ConsulTech

 

 

 

 

 

 

 

PAC

South Street Realignment (Rosalind to Orange Ave) – Construction Procurement

City

2009

2009

2009

 

PAC

Demolition Services Request for Proposals

City

2008

2008

2009

 

PAC

Last Round of Design Sub-Consultants Procurement (Building Controls, FF&E, Window Washing, Food Service, Enhanced Commissioning, & Wind Studies)

DPAC

7/2008

7 – 8/2008

8 – 9/2008

 

PAC

South Street Realignment (Rosalind to Orange Ave) – Design Services Request for Qualification Statements

City

6/16/2008*

7/2/2008*

9/8/2008

7/29/2008*

Lochrane Consulting Engineers and Surveyors Ranked #1, pending City Council Approval

PAC

Construction Manager at Risk Request for Proposals

DPAC

6/18/08 (Part 1)*

8/28/08 (Part 2)

8/14/08 (Part 1)

9 – 11/2008

Link to RFP Part 1 & Addendums; RFP Part 1 Responses Due Date has been revised from 7/23/08 to 8/14/08.

PAC

Wayfinding Graphics Consultant Request for Proposals

DPAC

5/13/2008*

6/5/2008*

7/16/2008*

Sussman/Prejza & Co., Inc. Ranked # 1, pending successful negotiations.

Link to Selection Notification

PAC

Audio/Video Consultant Request for Proposals

DPAC

5/13/2008*

6/5/2008*

6/27/2008*

 

Artec Consultants, Inc. w/ Quietly Making Noise, LLC. Ranked # 1, pending successful negotiations.

Link to Selection Notification

PAC

ADA/Accessibility Consultant Request for Qualifications

DPAC

2/12/2008*

2/29/2008*

6/3/2008*

Accessology selected (only proposal received), pending successful negotiations 

PAC

Reprographics and Document Management Request for Proposals

DPAC

2/12/2008*

2/29/2008*

5/13/2008*

Ranked # 1 Winter Park Blue with LDI Reproprinting Centers

PAC

Building Envelope Consultant (waterproofing, roofing, curtain wall, and window wall consultant) Request for Qualifications

DPAC

2/12/2008*

2/29/2008*

3/4/2008*

Ranked #1 Curtainwall Design Consultants

PAC

Elevator Consultant Request for Qualifications

DPAC

2/12/2008*

2/29/2008*

3/4/2008*

Ranked #1 Persohn Hahn Associates, Inc

PAC

Architectural Lighting Consultant Request for Proposals

DPAC

2/12/2008*

2/29/2008*

3/4/2008*

Ranked #1 Horton Lees Brogden Lighting Design

PAC

Sustainability Consultant Request for Proposals

DPAC

2/12/2008*

2/29/2008*

3/4/2008*

Ranked #1 Green Building Services

PAC

Food Service Consultant Request for Proposals

DPAC

12/21/2007*

1/18/2008*

3/4/2008*

Ranked #1 JGL Management Services Corporation

PAC

Public Relations Consultant

DPAC

12/18/2007*

1/18/2008*

3/4/2008*

Ranked #1 Edelman Inc. w/TJM Consultants, Inc.

PAC

Landscape Architects Consultant Request for Proposals

DPAC

12/21/2007*

1/18/2008*

2/5/2008*

Ranked #1 Murase Associates w/JCR Consulting

PAC

Mechanical/Electrical/Plumbing Engineering Consultant Request for Proposals

DPAC

12/21/2007*

1/18/2008

1/31/2008*

Ranked #1 TLC w/ARUP & SGM

PAC

Structural Engineering Consultant Request for Proposals

DPAC

12/21/2007*

1/18/2008*

1/31/2008*

Ranked #1 TLC w/ARUP, Brindley Pieters & Base

PAC

Code/Fire Protection Consultant Request for Proposals

DPAC

12/21/2007*

1/18/2008*

1/31/2008*

Ranked #1 Hughes Associates w/John J. Christie

PAC

Civil Engineering Consultant Request for Proposals

DPAC

12/21/2007*

1/18/2008*

1/29/2008*

Ranked #1 WBQ w/AVCON, Bobes & Faller Davis

PAC

Geotechnical Engineering Consultant Request for Proposals

DPAC

12/21/2007*

1/18/2008*

1/29/2008*

Ranked #1 Universal Engineering w/Law Associates

PAC

City ROW Survey Services, Continuing Services Agreement, Services Authorization

City

 

11/28/2007*

1/22/2008*

PEC Engineering

PAC

Production Architect Request for Proposals

DPAC

8/27/2007*

9/14/2007*

10/15/2007*

HKS/Baker Barrios selected

PAC

M/WBE Consultant Request for Proposals

DPAC

8/27/2007*